Delays plague Jones South renovations

A detached sink sits in Jones South during ongoing renovations. Work began over the summer and lasted through O-Week into the beginning of the school year due to delays caused in part by problems with piping.
After delays in Jones College construction, which was initially scheduled to finish before Orientation Week, Rice University Housing and Dining looks to finish basement and kitchen construction in the South section, according to H&D Associate Vice President Mark Ditman and Facilities, Engineering and Planning Manager of Communications Susann Glenn.
According to FE&P Senior Project Manager Anzilla Gilmore, the renovations included the addition of a first floor suite and study spaces, larger lobby spaces, upgrading restrooms, as well as various smaller fixtures.
Ditman and Glenn said the delays were in part due to new piping, water fixtures and redoing the bathrooms.
“We ran into a few of those hiccups along the way,” Glenn said. “The contractor recovered the best way that they could. It was truly a heroic effort the night before O-Week move-in. We had people on site until 5:30 a.m. It was incredible. Obviously that’s not an ideal situation, but the good news is we learned lessons.”
According to Gilmore, the cumulation of decay in Jones’ buildings resulted in the delays, which were resolved by August 23, the move-in day for all Rice students.
“The major factor that contributed to delays to the project was a general underestimation of the complexity of the renovation of a 57-year-old building,” Gilmore said. “Over the years, the building (particularly the restrooms) has suffered a lot of wear and tear, [whose] extents were not completely apparent until we started demolition. Once the issues were uncovered, additional design time had to be taken to properly address the best way to put the restrooms back together.”
The remaining renovations include those related to the kitchen and basement, which had a lower priority than students’ rooms, according to Ditman.
“The hall lobbies’ kitchenettes are being removed,” Ditman said. “Those have been consolidated into a larger room for studying and the remnant of the space will be more suitable for social things.”
Member of the Jones Renovation committee Mitch Torczon was not pleased the renovations were still in place during O-Week but praised Gilmore’s work in finishing up the construction within the week.
“I am disappointed that the renovation was not done before O-Week and that there is still some major touch up work being done,” Torczon, a Jones junior, said. “That being said, I have been very impressed at how hard Gilmore has been working to get things finished. [H&D] have really done an incredible amount the first week of school.”
Jones sophomore William Fernandez expressed frustration with the delays in construction, that displaced all new students in South section to North section for O-Week.
“It would be nice if H&D would finish something on time every once in a while,” Fernandez said.
Jones senior Kyle Denny, however, was overall pleased with the new renovations.
“I like how they color coded the floors — that really helps,” Denny said.
More from The Rice Thresher

Beer Bike canceled due to weather concerns
Beer Bike races were cut short on Saturday due to lightning warnings in the area.

Rice welcomes 7.8% of applicants to class of 2029
Rice accepted 2,852 applicants to the class of 2029 March 26, said Yvonne Romero, vice president for enrollment. This represents 7.8% of 36,777, the highest acceptance rate since 2022.

Engineering school celebrates 50th anniversary, invites students, alumni and speakers
The George R. Brown School of Engineering invited engineering alumni, students and faculty to celebrate its 50th anniversary March 28-29. The event, which took place in the Engineering Quad, included speakers, a drone show, alumni gatherings and other social events like mixers.
Please note All comments are eligible for publication by The Rice Thresher.